As computing requirements continue to increase, data centers become a more significant portion of the total worldwide load. The monitoring solutions for these data centers must be intelligent to maintain a reliable, safe, and efficient asset. In this case study, we will explore one such data center that utilizes the ETAP eSCADA/PMS solution to achieve an optimal data center. Etisalat, a multinational Emirati-based telecommunications provider operating in approximately 15 countries across Asia, the Middle East, and Africa, uses this data center.
AG Engineering and Power Contracting (AGEPC) is a specialized building services company that Enhances Life with Building Services. It offers reliable, sustainable, and innovative engineering services to the building and infrastructure industries, maintaining the highest quality standards, health, safety, and environmental protection. An AG Engineering and Power team has designed and delivered numerous regional data centers.
Location: Al Muteena, Deira, United Arab Emirates
Year: 2021
To build the largest and state-of-the-art Data Center in the Middle East
Which solutions did they choose?
They chose ETAP Digital Twin modeling with eScada and PMS to drive digital transformation and introduce digital solutions from design to implementation and operations. The digital twin model-based approach and an electrical integrated with power system design and power monitoring system were the main reasons that they chose the ETAP solution.
ETAP ensures compliance with all electrical design standards, calculations, maintenance, and operation.
Why do they use ETAP?
What do they think about ETAP?
ETAP has real-time applications, so when you go to the applications, you see various application levels. You can view the event playback network topology state, load estimation, real-time load flow, and real-time short-circuit switching management. It allows for early detection and announcement of problems before the critical failure takes place, which is the key element for any data center operation in terms of the client and operator's perspective.By S Sathik Batcha, Senior Operations Manager at AG Engineering
The ETAP eScada system solution was enabled with network modeling, simulations, analysis, and operational tools for designing, simulating, operating, controlling, and, of course, optimizing power network systems.By S Sathik Batcha, Senior Operations Manager at AG Engineering
As computing requirements continue to increase, data centers are becoming a larger portion of the total world-wide loading. It is critical that the monitoring solutions for these data centers are intelligent in order to maintain a reliable, safe, and efficient asset. During this presentation we will take a deep dive in one such data center utilizing the ETAP eSCADA / PMS solution to achieve an optimal data center.
ETAP Digital Twin
Arc Flash Analysis
Power Systems Analysis
Load Management System
ArcSafety™ - AC Arc Flash